This article mainly introduces the optocoupler products must pass the IEC 60747-5-5 optocoupler safety certification test items, including partial discharge test, isolation withstand voltage test, reliability verification test and other items, and provides a practical test method for each test item.
How do I do partial discharge testing under IEC 60747-5-5?
We useHT9464M TesterTwo steps:
- First add 6000V high voltage for 60 seconds (specific voltage depends on product specifications)
- Then drop to 1.5 times the operating voltage and hold for 10 seconds
Key indicator: Discharge must be <5pC (equivalent to 5 electrons)
The production line can be simplified:
- Time reduced to 1 second
- Voltage increased to 1.875 times the operating voltage
How to do the isolation withstand voltage test according to IEC 60747-5-5
Periodically, this test has to be done:
- Using the HT9464M (up to 10kVrms) tester
- Check that the insulation is intact
- Ensure safety after years of use
Reliability Verification
We are constantly "torturing" optocoupler products according to standard requirements:
- Back and forth from a high temperature of 85°C to a low temperature of -40°C
- 85% power-on test in humidity environment
- 1000 hours of continuous operation to see if it will break down
Test item abbreviation
“Reminder: swipe tables left and right”Parameter code
Test Item Description
typical value
VIOTM
Maximum transient voltage
6000V
VIORM
Maximum voltage for daily operation
4000V
New changes in the 2020 edition of IEC 60747-5-5
- New surge test: simulates lightning strikes and other sudden high voltages
- Allowed to mark the basic insulation class
- Replaces the old three standards, which are now standardized.
Attention:
- The certification body raids the production line every year
- Test equipment should be calibrated regularly
- Material changes must be retested

High Voltage Isolation Test Methods for Digital Isolators and Optocoupler Chips
What isolation safety approvals are required for digital isolators or optocoupler chips